Dominion Targets End-2027 Completion for Virginia Offshore Wind Farm

Offshore Engineer

Dominion Energy has updated the construction schedule for its 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, with installation of the 176th and final wind…

Dominion Energy has updated the construction schedule for its 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, with installation of the 176th and final wind turbine now expected by the end of 2027, while reporting the project was approximately 81% complete as of July 31.

Construction has continued to advance across the project's main components. All 176 monopiles and 176 transition pieces have now been installed, while 31 wind turbine generators have been completed and installation of the 32nd turbine is underway.

Fabrication is also nearing completion, with all nacelles, about 99% of towers and 85% of blades produced. The remaining towers are expected to be completed in the coming days, followed by the final blades in October, according to Dominion Energy.

The first and second offshore substations have completed commissioning, while the third and final offshore substation is expected to reach that stage by the end of 2026. Once commissioned, about half of the project's investment, excluding network upgrade costs, will have entered service.

The revised installation schedule incorporates additional contingency for weather, vessel maintenance, loadout operations and extended jacking activities. Dominion noted that the underlying turbine installation rate has remained unchanged at approximately two days per turbine over the

Content Original Link:

Read full article from Original Source OFFSHORE ENGINEER

" target="_blank">

Read full article from Original Source OFFSHORE ENGINEER

SILVER ADVERTISERS

BRONZE ADVERTISERS

Infomarine banners

Advertise in Maritime Directory

Publishers

Publishers