New Troll Project Start Up Boosts North Sea Gas Production

Offshore Engineer

Production has started from the Troll Phase 3 Stage 2 subsea project in the North Sea, adding gas supply to the 30-year-old Troll A platform and the Kollsnes processing plant…

Production has started from the Troll Phase 3 Stage 2 subsea project in the North Sea, adding gas supply to the 30-year-old Troll A platform and the Kollsnes processing plant.

The project started production on August 22 and is designed to accelerate production of 55 billion standard cubic metres of gas from the Troll West reservoir, equivalent to nearly two years of France's gas demand.

The project builds on the subsea facilities developed under Troll Phase 3, which began production in 2021, and reuses existing design and standardized solutions. It came on stream just over two years after the partnership's investment decision.

The Troll partnership comprises Petoro, Equinor, Shell, TotalEnergies and ConocoPhillips. Equinor is the operator with a 30.55% interest, while Petoro holds 55.93%, Shell 8.19%, TotalEnergies 3.69% and ConocoPhillips 1.64%.

"We start production with excellent HSE results, ahead of schedule and several hundred million Norwegian kroner below the cost estimate. The main reasons are efficient marine operations and a highly efficient drilling campaign, which was completed 25 per cent faster than planned," said Trond Bokn, senior vice president for project development at Equinor.

The eight-well drilling campaign was completed in five and a half months using Odfjell's Deepsea Aberdeen rig,

Content Original Link:

Read full article from Original Source OFFSHORE ENGINEER

" target="_blank">

Read full article from Original Source OFFSHORE ENGINEER

SILVER ADVERTISERS

BRONZE ADVERTISERS

Infomarine banners

Advertise in Maritime Directory

Publishers

Publishers